Cryomodule Refurbishment FAQ
Why should we refurbish CEBAF cryomodules?
CEBAF
availability at the desired beam energy is limited by cold window and
waveguide arc trips. These are thought to be caused by charging of the
cold ceramic windows by field emission. Installing doglegs in the cold
waveguide should eliminate this. Reprocessing cavities using the latest
techniques should also provide useful gradient improvement. Also about
half a dozen cryomodules have one or more cavities permanently bypassed
due to hurricane damage, helium leaks, tuner failure or other problems.
Is the cavity material
good enough to warrant reprocessing?
The
specification of the material is the same as presently used. Actual received
new material significantly exceeds those specs. Whether the number of
defects is comparable to present quality is unknown since production
processes have evolved over time. Many CEBAF cavities had quench limits
due to material defects or Q-switches so it is prudent to be conservative
when projecting gradient improvements. Field emission should be substantially
improved with current processes however.
Do we still have the
tooling?
Yes,
at least one set of all major tooling was put into storage after CEBAF
construction and preserved for just this eventuality. Some tooling will
need refurbishment and some smaller items will need to be replaced or
remade. Some changes may be desirable to take account of current assembly
practices, e.g. tooling to test single cavities (as opposed to cavity
pairs) in the VTA, or for CEBAF cavity electropolishing.
What does refurbishment
include?
Refurbishment
as currently proposed includes disassembly and reprocessing of the 5-cell
CEBAF cavities using the best available processes (including the options
of electropolishing and baking), reassembly with dog-leg waveguides,
improvements in magnetic shielding and replacement of all wearing parts
such as seals, tuner mechanisms etc. Reasonable efforts will be made
to minimize backlash in the rebuilt tuner assemblies. Any defective parts
or instrumentation will be replaced.
What is not included
in refurbishment?
New
cavities are not foreseen. If any are damaged or unusable for any reason
they will be repaired or replaced by the best of the old cavities in
storage. No changes to the HOM dampers are envisioned, or to the helium
vessel or indium seals. A major redesign of the tuner mechanism is not
included in this scope of work.
What performance gain
can we expect?
We
can reasonably expect an average gradient of about 12-13 MV/m, or ~50
MV per module after refurbishment. This is about double the average of
existing modules and more than twice that of the worst ones. Some cavities
may do considerably better, especially if electropolishing is successful,
however we may not be able to take full advantage of those without new
LLRF and higher power klystrons. The FEL03 module can operate at over
13 MV/m with beam with the same cell shape using existing LLRF and 8
kW klystrons, however the Lorentz detuning is large at this gradient
and recovery after a trip requires manual intervention, as does SL21.
We will have a better idea of the reach of refurbished modules after
the first few are re-commissioned.
How much does it cost?
Restarting
the process, including gathering up all the tooling and refurbishing
or replacing missing items, reestablishing the chemistry, HPR and clean
assembly processes for the CEBAF geometry, evaluating the electropolishing
option and training or retraining the assembly crews is estimated to
take about $150k in procurements and $125k in labor in the first part
of FY05. Note that this is less than originally projected as all the
major tooling has been identified and found to be in quite good condition.
Preliminary estimates for module refurbishment add up to $250k procurements,
$450k assembly labor, $50k engineering support and $250k for infrastructure,
QA, management and testing for a total of $1M/module. The procurements
and a small fraction of the labor may come from AIP funds, the remainder
must come from the nuclear physics budget. A more detailed estimate is
being prepared in anticipation of the FY05 budget cycle.
Is the cost of some
refurbishment included in the 12 GeV upgrade?
No,
the 12 GeV project assumes a stable base machine. There may have been
some conservatism in the 12 GeV spec. to allow for a base machine of
less than 6 GeV, but there are no project funds to upgrade or maintain
the existing stock of cryomodules.
Why not do the whole
12 GeV upgrade by refurbishment?
While
it is clearly advantageous to refurbish some number of cryomodules to
achieve stable 6 GeV operation ahead of the upgrade, estimates consistently
indicate that it is more cost effective to switch to building new modules
in new zones once project funds become available and the stock of underperforming
old modules is used up. The exact crossover point will depend on the
level of success of refurbishment and the exact cost of new zones.
Where will it be done
and by whom?
Cryomodule
refurbishment will be done in the test lab by the usual cast of characters.
Once SNS production is finished and the Renascence cryomodule is
assembled, the assembly areas will be used mainly for CEBAF module
refurbishment, with some other work such as the new FEL injector cryomodule,
R&D
tests and work for others. The areas originally used for cryounit
assembly are now occupied by the electropolish facility and the CMM
room. We are currently searching for alternative spaces. Candidates
include the area presently occupied by the SNS 1 MW klystron, the space
in the test lab annex presently used for vacuum assembly and the area
outside the CMTF control room presently being used to store a large
detector. Proposals to eliminate the test lab annex tech shop, apart
from destroying an essential asset, will exacerbate the space shortage
and limit or eliminate access to the downstairs assembly area and upstairs
weld shop and parts processing areas.
When can we start
and how long does it take?
The
first module will be available to refurbish around May 05. This is
consistent with the roll off of SNS work and availability of assembly
technicians. The cavity production group will finish with SNS work
earlier and can begin setting up the cavity reprocessing facilities
and practice on old 5-cell cavities. The present request is for us
to refurbish two modules per year in steady state, far less than the
original CEBAF construction rate. The first refurbished module should
be ready in the first half of FY06 and when that one is installed we will start work on
the one that comes out. A detailed plan is being prepared in anticipation
of the FY05 budget cycle.
When will we have
stable 6 GeV?
According
to Jay’s LEM predictions we should reach 6.0 GeV at 10 FSD/hr with
Renascence plus two refurbished modules installed and all systems up
and running. To provide “stable” 6 GeV, i.e. with some headroom,
we should refurbish at least two more modules and consider at least one
per year thereafter to keep up with attrition. The trip rate
at 12 GeV will be no better than the base 6 GeV machine unless we assume
some contingency in the 12 GeV, so the more modules we can rework the
better for the long term physics program.
How high in gradient
can we go with the existing LLRF system?
The
existing LLRF system operates in the FEL at 13.5 MV/m and maintains
stable gradient with 8 kW klystrons. The FEL tuners have practically
no hysteresis so the tuning limits are set very close in. Depending
on the Qext’s
and the detuning and microphonics allowances the system might be able
to operate even a little higher. With the original CEBAF cavities, HPA’s
and tuners the system will run out of RF power before reaching the
limit of the LLRF.
Why do we need a new
LLRF system?
The
existing LLRF cannot handle the high Q’s and large Lorentz detuning
of the new-style cryomodules. It is also obsolete and unsupportable and
the stock of spares is rapidly diminishing. A new system is needed
just to maintain the existing machine and is essential to operate new
style cryomodules to their full potential. A requirement of the new
system is that it must be capable of running old-style modules and
eventually will be retrofitted to existing zones as spare parts for
the old systems are exhausted. A new system can also take advantages
of the latest thinking in algorithm development, tackle microphonics
through electronic damping and piezo feedback and give much better
diagnostics of RF system health. And be more economically maintained.
Is it worth installing
new LLRF or high power klystrons in refurbished zones?
Depending
on how successful we are with cavity reprocessing it may be cost effective
to populate refurbished zones with new LLRF and the best existing klystrons.
In any case if old LLRF systems are to be replaced due to attrition it
makes sense to put the new LLRF into the refurbished and best existing
zones first.
|