SNS
Construction

As part of a multi-laboratory collaboration, Jefferson Lab is currently
engaged in the fabrication, assembly, and testing of 23 cryomodules for
the superconducting linac portion of the Spallation
Neutron Source (SNS) being built at Oak
Ridge National Laboratory. The superconducting linac is designed
to accelerate protons to an energy of 1 GeV onto a mercury target. Eleven
of these cryomodules will each contain 3 medium velocity ( b=0.61) superconducting
RF cavities, with the remaining twelve each containing 4 high velocity
( b=0.81) superconducting RF cavities. In addition to superconducting
cavities, the cryomodules contain tuner mechanisms, power couplers, diagnostic
and control instrumentation, and cryogenic circuits.
In order to achieve the required energy of 1 GeV within the limitations
of the RF and cryogenic system parameters, the cavities used in the medium
(high) beta cryomodules must achieve an average gradient of 10.2 (15.6)
MV/m at a Q-value of 5 x 10 9. These gradients correspond to peak surface
electric fields of 27.6 (34.2) MV/m. While these surface fields do not
represent the state-of-the art achieved in R&D or prototype cavities
worldwide, for the high beta cavities they represent the highest surface
fields specified for a production SRF installation to date. The cavities
processed and tested for the SNS cryomodules, which were fabricated by Accel
Instruments Gmbh in Germany, have not only met these required specifications,
but in fact exceeded them in many instances, with the highest peak surface
electric fields measured at 54.2 (56.5) MV/m for the medium (high) beta
cavities.
The excellent cavity performance obtained during vertical testing has
been preserved in the final cryomodule assembly. For the medium beta
cryomodules, of which seven were extensively tested, the average peak
(accelerating) electric field of the cavities is 41 (15.1) MV/m, which
exceeds the required performance by almost 50%. Similarly, for the cavities
in the two high beta cryomodules tested, the average peak (accelerating)
electric field of the cavities is 43 (19.6) MV/m, which exceeds the required
performance by 25%.
Cryomodule performance is characterized by more than just the performance
of the cavities installed in the module however, as overall performance
is the product of numerous distinct elements that must work in concert
to achieve the operational capabilities and stability required when the
cryomodule is installed in the linac. The cryomodules fabricated and
assembled for the SNS project meet or exceed required performance specifications
in the areas of HOM (higher order mode) extraction, input coupling, tuner
operation, and sensitivity to microphonics (environmental disturbances).
For example, the FPC performance is characterized by its ability to deliver
power to a cavity without arcing or vacuum problems. Only 6% of the cavities
tested were limited by coupler performance (and at a level greater than
that needed to achieve required cryomodule performance). In addition,
extensive measurements of the cavity response to Lorentz forces were
performed. In general, the cryomodules met or exceeded the requirements.
It was also shown that the additional use of the piezo tuner was a simple
and effective method of reducing the sensitivity of the cavity to Lorentz
forces.
The JLab production of SNS Cryomodules is scheduled and on track for
completion in March 2005, when the 23 rd production module will be shipped
to Oak Ridge, Tennessee.
Jefferson
Lab joined the Spallation Neutron Source collaboration
in February 2000. The accepted work scope included:
|
Scope Element |
Status |
1 |
An R&D
program to
determine parameters and specifications for
the production of cavities and cryomodules, fabricate and test
four medium-β (β = 0.61) and two high-β (β = 0.81)
six-cell cavities, and fabricate and test a three-cavity prototype
cryomodule.
|
Completed September 2002 |
2 |
Design and construction of
a cavity/cryomodule production facility capable of producing/repairing five cryomodules/year.
|
Descoped as a cost-saving measure after design
was complete (November 2000). |
3 |
Design and procure/construct
a helium refrigerator and helium distribution system.
|
Completed December 2004 |
4 |
Design and procure/construct 11 three-cavity medium-β cryomodules.
Originally, two of these cryomodules were to be tested at JLab.
This scope was subsequently expanded to the testing of seven cryomodules.
|
Completed May 2004 |
5 |
Design and procure/construct 12 four-cavity high-β cryomodules.
Originally, one of these cryomodules was to be tested at JLab.
This scope was subsequently expanded to the testing of two cryomodules.
|
Projected completion March 2005 |
The staff at the SRF Institute has been working hard on
completing the SNS project. A 2003
JLab News Release explains more about the SNS project.